Raithwaite Hall, Whitby
Raithwaite Hall, Whitby

Raithwaite Hall Construction Progress

To view photos, plans & elevations of this development, click the thumbnails below to enlarge.

Project Time Line

05/10/2010 Roof structure built and old build felt and battening on.
20/09/2010 Floors constructed and poured.
05/09/2010 Steel frame erected.
20/08/2010 Building 5 and 4 demolished, pad foundations for steel poured.
05/08/2010 Swimming pool formed ready for concrete.
20/07/2010 Car park tarmac base course.
20/07/2010 Steel framework for swimming pool and gym placed in position.
14/07/2010 Roof strip.
05/07/2010 Roof structure stripped and chimneys rebuilt.
01/07/2010 Scaffolding erection on existing building.
20/06/2010 Block work to existing building and continue bulk excavation.
14/06/2010 Internal structure work.
05/06/2010 Bulk excavation.
20/05.2010 Car park edging and underpinning old building.
11/05/2010 Bulk excavation.
01/01/2010 Planning condition release, surveys, ground investigations and mobilisation.
01/02/2010 Decanting existing use.
01/03/2010 Site clearance and set up.
22/03/2010 Asbestos removal, services disconnection and surveys.
12/04/2010 Soft strip and demolition.
26/04/2010 Car park marking out and initial muck shift.
04/05/2010 Pilling foundations.

Bookmark and Share


© 2010 Skelwith Group Ltd. All Rights Reserved.  Legal Information  |  Privacy Policy  |  Disclaimer

Skelwith Leisure Ltd, Skelwith Property Management Ltd, Skelwith Interiors Ltd
and Skelwith Commercial are all part of the Skelwith Group Ltd

Created by Happyleaves »